Realizations from 1999 to 2002
Period |
Customer |
Realizations |
| 1999 to 2001 |
SOSETRA
Bel Air Dakar |
Fabrication and erection of a shed of 20 000 m2 and installation of machinery for foundry and rolling mill in MBAO
|
SOGEPAL
Rue 7 ZI Dakar |
Building of a plant of Biscuit factory km 4.5 Boulevard of the centenary of the Village of Dakar and supply and erection of a shed of 20 000 m2
|
| 2001 to 2002 |
CCS
Malick Sy Avenue -DAKAR |
Construction of a Building for Warehouses, Basement + ground floor + 6 Floors of 22 000 m2 of cover area Including 405 Piles of 500 and 650 mm diameters and 16.50 meter deep.
|
Realizations from 2003 to 2004
Period |
Customer |
Realizations |
| 2003 |
Industrie chimique du Senegal
Dakar |
Construction of skirt wall for a storage tank at ICS Mbao.
|
| 2003 |
Cement de Mauritanie
Tambacounda |
Construction 75TPH cement grinding unit at Nouakchott, including, Piles, civil work, supply and erection of steel structure, erection and commissioning of mechanical equipments.
|
| 2003 to 2004 |
Immeuble aux 4 vents
Bel Air -Dakar |
Construction of commercial building Basement+ground floor+ three floors on turn key basis. |
| 2003 to 2004 |
Projet agroforestier de lutte contre la désertification
Diourbel |
Drilling of 19 bore well in the region of Diourbel - Senegal
|
Realizations from 2005 to 2006
Period |
Customer |
Realizations |
| 2005 |
Comptoir commercial Mandiaye Ndiaye
Dakar |
Design, supply and construction of 8500m2 storage hanger, including all the civil and earth work.
|
| 2005 |
PNIR
Tambacounda |
Drilling of 7 bore well and other infrastructure and supply of hand pump India mark II.
|
| 2006 |
Résidence lacoste
Dakar |
Work of demolition and re-habilitation of old building in the heart of city
|
| 2006 |
Projet Agroforestier de lutte contre la désertification
Diourbel |
Realization of 15 km of adduction in drinking water and a catchment basin in the region of Diourbel - Senegal
|
| 2005 to 2006 |
BSA Cement
Nouakchott |
Construction of 80 TPH cement grinding unit complete with pilling, civil work, supply and erection of steel structure and erection and commissioning of mechanical equipment.
|
Realizations from 2007 to 2009
Period |
Customer |
Realizations |
| 2007-2008 |
Office Nationale d'assainissement du Sénégal
Dakar |
Sewage system for city of LOUGA and construction and commissioning of Sewage treatment plant.
|
| 2007-2008 |
HARSTAND SENEGAL SA
Dakar |
construction of the Building PARADISE ROCK - Earthwork - Moulded Walls of protection - special Foundations
|
| 2007 |
Atelier de rénovation technique ( BIA SENEGAL)
Dakar |
Realization of the civil engineering of a Workshop and a Training centre in MBAO
|
| 2007-2008 |
Immeuble Acile Center
Dakar |
Construction of residential and commercial building basement + Ground Floor + 6 floors
|
| 2007 |
Direction de l'hydraulique
Matam |
Realization of 4 bore well and 2 Piézomètres in the localities of the Axle Notto-Ndiosmone-Palmarin
|
| 2007-2008 |
Immeuble S.A.I.M NONI
Dakar |
Construction of residential &commercial Building in down town, basement + Ground Floor + 8 floors
|
| 2007 |
Compagnie Sucrière Sénégalaise
Matam |
Pilling and civil foundation work for distillery in sugar mill at Richard Toll.
|
| 2007 |
S.C.I LOUNAKE
SENEGAL |
Construction of residential building basement + G.F + 1 floor
|
| 2007-2008 |
Foncière côte d'Afrique
Rufisque |
Construction of building consisting of 4 twinned villas RESIDENCE ATHENEE BASEMENT common + G.F + 1 floor
|
| 2008 |
SOCOCIM INDUSTERIES
Dakar |
Construction of civil work (LOT B SOCOFA 1485) for 1MTPA clinker unit-5
|
| 2008 |
Agronomes Vétérinaires Sans Frontières
Matam |
Realization of 1 bore well in the region of MATAM
|
| 2008 |
PRODAM II
Matam |
Realization of 2 deep boring in the region of MATAM |
| 2008 |
Arcelor Mittal Mining Sénégal
Dakar |
Construction of 27 km of lane NAFADJI and BOFETO , Construction of a 30mtr long bridge in BOFETO over a river Realization of 11 Boring equipped with pumps
|
Realizations from 2009 to 2010
Period |
Customer |
Realizations |
| 2009-2010 |
CCS YOFF
Dakar |
Construction of 2 buildings with commercial usage Basement + RDC + Mezzanine + 6 Floors, on the road of the Airport - YOFF
|
| 2009 |
MOUSSA KHAZEN SHAHARA
Dakar |
Construction of commercial building, basement + G.F + 6 floors
|
| 2009 |
IPC MBAO
|
Construction of 6600 sq mtr hanger with office block at Mbao.
|
| 2009-2010 |
CSS Richard Toll
|
Construction of civil work 20MW power plant.
|
| 2009 |
SOCOCIM Industries
Rufisque |
Erection of steel structure and mechanical equipment for 1million TPA new clinker unit for SOCOCIM( SOCOFA ,1485- Lot A + Lot B) including complete Refractory and insulation work.
|
| 2009 |
Direction de l'hydraulique
Dakar |
Realization of 10 deep bore well in the regions of Thies and Louga
|
| 2009 |
Direction de la gestion et de la planification des ressources en eau
Matam |
Realization of 04 piézomètres in the regions of Thies and Louga
|
| 2009 |
Direction de la gestion et de la planification des ressources en eau
Dakar |
Realization of 03 piézomètres and rehabilitation of 10 piézomètres in the regions of Diourbel, Kaolack, Matam, Tambacounda, Kolda and Dakar
|
|
|
|